Industrial plant construction for new production hall
We have recently collaborated with Trafilerie Alluminio Alexia, a manufacturing company focused on aluminium processing, which entrusted Pedroncelli S.r.l. the construction of essential facilities for the company's new production unit.
Challenge:
After the construction of the building, the challenge was ensure the correct implementation of the methane/LPG gas, compressed air and fire-fighting systems in a very tight timeframe, demonstrating maximum availability and flexibility in site management.
Technical details:
- the LPG/methane system was realised with yellow pre-painted steel pipes conforming to gas passage in diameters DN 50/80/100 for the above-ground parts; for the indoor parts we used polyethylene pipes.
- the fire-fighting system was built with polyethylene pipes for water transport in diameters 125/90/75. For the external part we used cast-iron underground hydrants; for the internal part we used wall hydrants both with 20 m hoses.
- the compressed air system was realised with blue pre-painted aluminium pipes in diameters 63 for the main part of the backbone and diameters 32 for the down conductors.
The job was successfully completed with a team on hand for all stages of the work, confirming the technical capabilities that make us a leading company in the field of plant engineering in province of Sondrio and northern Italy. We are grateful for the trust of our customers and ready to meet the needs of future ones.